On May 4th construction crews will take southbound traffic and put them into the current northbound lanes from Ivyland Rd. to Meyer Way (Warwick Twp.). This will be a long term traffic pattern with a single lane each way and a center turning lane along the length of the work zone.

This stage of construction will be in effect until approximately September 2016. Access will be maintained to all side roads, homes, and businesses on York Rd.

The section of Bristol Rd between York Rd. and Old York Rd. is tentatively scheduled to close sometime after June 1st. This will allow construction crews to begin reconstructing the intersection of York Rd and Bristol Rd. More details will follow as we get closer to a realistic start date for this phase.